ConTech · Jul 14
ModerateHudson Tunnel team approves an $88M change order to cut boring risk
The group building the Hudson Tunnel approved an $88 million change order. The extra work will clear old obstacles from the path of the tunnel boring machines. Crews will also mix lightweight concrete into the riverbed to firm up the soil. Kiewit's Weeks Marine is already in the river and starts later this year. Leaders called it a way to head off risk before boring begins.
Why it matters to GCs
This shows the value of spotting risk early and writing it into a clear change order. Fixing soft ground now costs far less than a stuck machine later. On your own jobs, name the risk, price the fix, and get it in writing before work starts.
Construction Dive·Via POLR AI Hub